Globalfoundries has announced it is moving forward with the final construction for the extension of module 1 at the Fab 8 campus in New York. Thanks to expansion of cleanroom space by about 1/3, the Fab 8 will be able to produce around 60 thousand 300mm wafers per month by the end of 2013 and will therefore be more competitive.

“During the construction of Fab 8, we extended the shell of the Module 1 building with the expectation that our business would continue to grow. Today we see increasingly strong demand from our customers, especially at the 28nm node, and we are excited to be moving forward with this next phase in the development of the Fab 8 campus,” said Eric Choh, vice president and general manager of Fab 8 at Globalfoundries.

The project will add 90 000 square feet (8361m2) of cleanroom space manufacturing capacity, bringing the total cleanroom space capacity for Fab 8 Module 1 to 300 000 square feet (27 870m2). Construction activities are scheduled to begin in August and work is expected to be completed in December 2013. Extending the Fab 8 cleanroom is expected to increase the Fab 8 capacity to approximately 60 thousand 300mm wafers per month and increase the capital budget by approximately $2.3 billion, taking the total capital budget from $4.6 billion to approximately $6.9 billion, once tools and equipment are installed.

When Globalfoundries' leading-edge Fab 1 capacities in Dresden, Germany, and Fab 8 capacities in the U.S. are fully ramped by early 2014, the company will be able to process 140 thousand of 300mm wafers using 20nm and 28nm process technologies per month; or 420 thousand of wafers per quarter. In addition, Globalfoundries has Fab 7 300mm facility in Singapore, which produces chips using 40nm, 45nm, 65nm, 90nm and 130nm process technologies. The Fab 7 capacity is 50 thousand 300mm wafers per month, or 150 thousand of wafers per quarter.

“By continuing to expand our investment in the project, Globalfoundries is delivering more options to our global customers, while helping to redefine upstate New York as a premier hub of the global semiconductor industry, creating thousands of new advanced manufacturing jobs, and contributing billions of dollars to the regional economy," added Mr. Choh.

Consisting of approximately two million square feet, Fab 8 is being developed as the world’s most advanced semiconductor foundry manufacturing facility and is consistently hitting all major development milestones. GLOBALFOUNDRIES began construction on Fab 8 in July 2009 and began moving people and equipment into the facility in mid-2011. Initial wafer starts began earlier this year and the facility is on track to begin risk production by the end of the year, with volume production in early 2013.

Tags: Globalfoundries, Semiconductor, 300mm, fab 8, 20nm, 28nm

Discussion

Comments currently: 1
Discussion started: 07/25/12 05:43:49 AM
Latest comment: 07/25/12 05:43:49 AM

[1-1]

1. 
Let's hope that the world economic situation improves as current conditions are not likely to support more GloFo expansion.
0 0 [Posted by: beenthere  | Date: 07/25/12 05:43:49 AM]
Reply

[1-1]

Add your Comment




Related news

Latest News

Monday, April 14, 2014

8:23 am | Microsoft Vows to Release Xbox 360 Emulator for Xbox One. Microsoft Xbox One May Gain Compatibility with Xbox 360 Games

Tuesday, April 1, 2014

10:39 am | Microsoft Reveals Kinect for Windows v2 Hardware. Launch of New Kinect for Windows Approaches

Tuesday, March 25, 2014

1:57 pm | Facebook to Acquire Virtual Reality Pioneer, Oculus VR. Facebook Considers Virtual Reality as Next-Gen Social Platform

1:35 pm | Intel Acquires Maker of Wearable Computing Devices. Basis Science Becomes Fully-Owned Subsidiary of Intel

Monday, March 24, 2014

10:53 pm | Global UHD TV Shipments Total 1.6 Million Units in 2013 – Analysts. China Ahead of the Whole World with 4K TV Adoption

10:40 pm | Crytek to Adopt AMD Mantle Mantle API for CryEngine. Leading Game Developer Adopts AMD Mantle

9:08 pm | Microsoft Unleashes DirectX 12: One API for PCs, Mobile Gadgets and Xbox One. Microsoft Promises Increased Performance, New Features with DirectX 12

3:33 pm | PowerVR Wizard: Imagination Reveals World’s First Ray-Tracing GPU IP for Mobile Devices. Imagination Technologies Brings Ray-Tracing, Hybrid Rendering Modes to Smartphones and Tablets

2:00 pm | Nokia Now Expects to Close Deal with Microsoft in Q2. Sale of Nokia’s Division to Close Next Month