Morris Chang, chief executive officer and chairman of Taiwan Semiconductor Manufacturing Co., said that his company will initiate volume production of chips using 20nm process technology at its Fab 14/phase 5 manufacturing facility in February, 2013. The company will also be producing chips using 20nm fabrication process at its Fab 15/phases 3 and 4 starting from May, 2014.

“On 20nm [process technology], we see little competition. The risk production has started in the first quarter [2013] and the volume production will start in early 2014 next year […] the equipment [is] already being installed, the equipment [is] streaming in and [is] being installed. […] The volume production will start in early 2014,” said Morris Chang, the head of TSMC, during quarterly conference call with financial analysts.

TSMC began to build the phase 5 of its Fab 14 in early April, 2012. The construction of the facility is now complete and the equipment has been being installed since April. It typically takes from six to twelve months to fully equip a semiconductor fab. The Fab 15/phases 3 and 4 will initiate production using 20nm process tech sometimes in May, according to Mr. Chang. Eventually, TSMC will also make chips using the 20nm technology at its fab 12/phase 6.

It is believed that a lot of equipment that will be used for making 20nm chips will be used to make semiconductors using 16nm FinFET manufacturing technology sometimes in 2015.

“On 16nm FinFET, it will start volume production about one year after 20nm SOC, in other words, early in 2015. Our R&D progress on 16 FinFET is very good, new improvement, is better than plan, and is better than 20nm a year ago. […] We have been working with several major customers and many tape-outs, many product tape-outs are,” said Mr. Chang.

 

Tags: TSMC, Semiconductor, 20nm, 16nm, 300mm

Discussion

Comments currently: 1
Discussion started: 08/08/13 10:29:19 AM
Latest comment: 08/08/13 10:29:19 AM

[1-1]

1. 
...volume production of chips using 20nm process technology at its Fab 14/phase 5 manufacturing facility in February, 2013.
You mean February 2014, right?
---
Fab 12/Phase 6 => ~5,000 wafer starts after June 2013, ~10,000 wafer starts after September 2013, ~30,000 wafer starts after January 2014.

Fab 14 and Fab 15 getting accelerated just means we will see 20nm earlier than expected.
0 0 [Posted by: seronx  | Date: 08/08/13 10:29:19 AM]
Reply

[1-1]

Add your Comment




Related news

Latest News

Thursday, August 28, 2014

12:22 pm | AMD Has No Plans to Reconsider Recommended Prices of Radeon R9 Graphics Cards. AMD Will Not Lower Recommended Prices of Radeon R9 Graphics Solutions

Wednesday, August 27, 2014

9:09 pm | Samsung Begins to Produce 2.13GHz 64GB DDR4 Memory Modules. Samsung Uses TSV DRAMs for 64GB DDR4 RDIMMs

Tuesday, August 26, 2014

6:41 pm | AMD Quietly Reveals Third Iteration of GCN Architecture with Tonga GPU. AMD Unleashes Radeon R9 285 Graphics Cards, Tonga GPU, GCN 1.2 Architecture

Monday, August 25, 2014

6:05 pm | Chinese Inspur to Sell Mission-Critical Servers with AMD Software, Power 8 Processors. IBM to Enter Chinese Big Data Market with the Help from Inspur

Sunday, August 24, 2014

6:12 pm | Former X-Bit Labs Editor Aims to Wed Tabletop Games with Mobile Platforms. Game Master Wants to Become a New World of Warcraft